05.h.1What should a first exhibition budget include before the design is fixed?

The first exhibition budget can be built from the works, the spaces and the time people will spend making and running the show. Include artist fees and production, preparation of borrowed works, transport, fit-out, technical hire, public running costs and dismantling. Name who pays each cost. A wall in a drawing may affect the budget for two teams if one builds it and another needs to move, light or remove it. Welsh Government, Costing Exhibitions

Put the uncertain items next to the decisions

For each work still under development, enter the last date on which its dimensions, weight or conditions can change without affecting other orders. A lender’s requirements may alter the design of a case or the method of transport. The National Gallery’s loan conditions illustrate how packing, transport and other responsibilities can be specified in advance. Ask the registrar to bring comparable information for each proposed loan before an allowance becomes a fixed price. National Gallery, loan conditions

The costs of two layouts can be compared using the same works and opening hours. Record the costs both designs share and the costs each one adds. One may need a longer installation period while another requires a member of staff to operate an extra room for the whole run. Give significant unknowns a provisional amount, an owner and a date for checking them. Keep the estimate through opening and return to it after dismantling, when the team knows what it paid to clear and store the installation. ICOM UK, touring exhibition agreement and guidance

An early exhibition budget can carry labour and storage after the closing date. The Gallery Climate Coalition discusses reclaimed materials and later reuse, and the Centre for Sustainable Curating follows design through deinstallation. The budget can separate removal, packing and the space needed to hold parts that are due to travel from the initial cost of making them. A supplier can then price a joint, label or protective layer according to what needs to be saved and who will handle it at the second location. Those costs can be attached to the display’s dismantling and reuse plan. Gallery Climate Coalition, Exhibition-making and display Centre for Sustainable Curating, Using the Resources at Hand