A hotel staying open during refurbishment can plan phases around the rooms it can sell, the utility zones, and the routes it can keep separate from guests. Count the rooms the operator can actually sell in each phase, including rooms lost to noisy work in adjacent bays and accessible room types taken offline. Agree what the builder, hotel engineer, housekeeping, and front office must verify before a room goes back into use.
Count the rooms tied to the same service
WPC’s account of renovating an occupied Courtyard and Residence Inn in Lake Nona records rolling closures of one or sometimes two floors, coordinated with hotel management. Look at the existing risers, isolation valves, and electrical zones to see whether an equivalent floor-by-floor plan is possible. The boundary between open and closed rooms may run vertically through the building. A room on an untouched floor can still lose hot water if it shares the branch being replaced. WPC, From Lobby to Guest Room, Tavistock Hotel Renovation, 2025
At Holiday Inn Hemel Hempstead the contractor reports three bedroom handovers of roughly 50 rooms and temporary reception and dining arrangements during the work. Architects’ Datafile describes how ReardonSmith developed a three-phase solution at 11 Cadogan Gardens, where the hotel was to stay open. Consider which parts of the brief depend on the lobby, restaurant, or elevator left open each day. A room can be ready by the builder’s definition while the route to it through reception is still unavailable. Murray & Willis, Holiday Inn Hemel Hempstead James Parker, Architects’ Datafile, Revealing Victorian Secrets at 11 Cadogan Gardens, 2016
Agree the reopening conditions before the first closure
The RIBA Plan of Work identifies construction and handover as distinct stages and recognizes that handover activity can overlap construction. For an occupied property, a phase has its own handover. Get the hotel to agree in advance which services must be tested, how repairs and cleaning are checked, and who releases the room into the booking system. Give the front office a hold that remains visible until release. An accessible room advertised with particular equipment should be checked for those features before it is assigned again. RIBA Plan of Work 2020 Overview
If work overruns, the operator needs a separate plan of which guest rooms, routes, and services can still operate with fewer rooms for sale. List the room types that must remain open and the positions that can take a replacement booking if a closure expands. Track the rooms that cannot be sold at any expected stage because of dust, noise, drying time, or system tests. Present the cost estimate with a room-night schedule so the owner can compare the phasing options in operational terms.
In a hypothetical five-floor hotel with 20 rooms to a floor, closing one floor would remove 20 rooms from sale. If work on a shared riser also takes four rooms above and four below, the closure removes 28 for the duration of the outage. Show those rooms on the section and state when they come back into use. If the eight further rooms include the property’s only rooms with a particular access feature, the sequencing decision affects room mix as well as total inventory. The reservations manager needs both figures before confirming the next release.
Fix a pilot stack or bay before releasing the largest group of rooms. Confirm that one vertical isolation can be made as planned and how trades pass through the service route. Ask the room manager to run the opening check after the first phase and put the differences into the next tender or work instruction. The most useful phasing plan includes a clear description of the hotel that will operate on the morning after each closure.