09.b.3Where should an operable wall’s panels park when the room is open?

The full panel stack needs somewhere to stay while people use the open room. A plan can show whether the widest panel can reach that position and whether the operator can stand there and open the pocket door. A section can show what supports the track and how a technician will reach it. The venue can approve the position once it sees the supplier’s panel sequence in the furnished room.

Find the first turn into the pocket

A stack near the opening gives each panel a short trip. It also takes up one end of the opening, which may be where people enter the combined room or turn around a piece of furniture. A branch track can take the panels past that junction to a separate pocket. The added length brings its own question. Put the operator beside the panel on the plan and walk them from the wall to the stack. Keep the route people will use after the room opens visible on the same drawing. In a proposed hall, a panel might clear the end of a counter and still leave too little room for the person holding its handle to make the turn. Move the stack or the counter while both positions can change.

At New York’s United Nations International School cafeteria, the manufacturer’s case study identifies 19 panels across two openings in a design by Skidmore, Owings & Merrill. Its floor plan shows a curved opening, an overhead track and a separate panel docking bay. The drawing is useful because it shows where the panels travel once they leave the dividing line. To compare a remote pocket with a stack beside the opening, draw the complete route for each and count the doors and other circulation it crosses. Set the two plans beside the proposed open-room seating. A route that is short on paper can be slow to operate if furniture must first be moved away from the turning point. NanaWall, United Nations International School cafeteria, plan and project account

Ask the supplier for the operating clearance at the junction as well as the parked footprint. The Kelly Walsh High School construction specification in Wyoming asks for both stacking and operating clearances, with the direction of travel, track and hardware shown on shop drawings. For a pocket with a cover, draw the leaf in its open position and the operator reaching the last panel. Keep that geometry on the furniture plan so a full room can be checked against it before the locations of adjacent fittings are fixed. Kelly Walsh High School, project manual, volume 2, section 10 22 26

An inside view of the pocket can show how the panels fit once they are parked. Check whether a handle or trim narrows the opening once it is fitted, and put the finished dimensions on the shop drawing. If a panel has a different width because it contains a door, give it an explicit position in the stack and check whether it needs to come out first or last when staff close the room again.

Draw the ceiling over the loaded stack

With top-hung panels, the load follows the track and concentrates around the parking location when the wall is open. Dormakaba’s instructions for its HSW-R glass system ask the installer to confirm support for the panels in the partition and stacking areas. The French association CERFF describes an assessed family of movable walls whose panels hang from rails attached to the building structure. Use the selected product information to establish how the proposed assembly works. Put the structural support, track and ceiling finish on a section at the stack, then add the nearest duct and the access needed to inspect the switch or hanger. Dormakaba, HSW-R Installation, 2004, p. 1 CERFF, definition of assessed movable walls and rail attachment, in French

Wake County Public School System’s design guidelines ask for track switches, track loads and stacking sizes in the operable-partition submittal, and call for coordination with structural steel shop drawings. Do the equivalent at the point when a supplier can give the structural engineer a layout and actual panel weights. Include any pass door built into a panel. Where a remote pocket takes the track into another bay, check the receiving supports there and at the transfer. Put the position of a removable ceiling panel on the coordinated section. A technician later needs to reach the place where the wall changes direction. Wake County Public School System, Design Guidelines 2024 to 2025, section 10 22 39

Give the operator a plan showing the order of parking and retrieval. Once the panels are installed, lay out the furniture closest to the pocket and ask the people who will work the wall to park every panel in order. Watch the approach of the last panel, when the pocket is nearly full. Have staff close the pocket and walk the public route through the open room. If the cover or the operator’s turning space occupies the aisle, adjust the layout and repeat the move before accepting that arrangement.