09.f.3Who draws and prices the connections between the building and modular furniture?

When modular furniture connects to the building, the lead designer can draw the connection and reference the same detail in both tender packages. Each package should say who designs and supplies its side and who makes and tests the final connection. The cost consultant can then price the work across the packages. A floor box, the cable from the furniture, and the work of connecting them may have three prices and two installers.

Follow the power to the tabletop

The August 2017 US Department of Defense guide specification for systems furniture gives one example of how to divide the drawings. Its drafting notes call for separate furniture power drawings from the electrical engineer and coordination of receptacle numbers and positions with the interior designer. The furniture installation drawings are to reflect field conditions and show affected building services. Use that division to structure a tender detail. Draw the table and how people approach it, then give the point of supply a dimension from a building reference that both installers can identify on site. USACE, NAVFAC and AFCEC, UFGS 12 59 00 Systems Furniture, August 2017, submittals and drawings

In the workshop of the Diriyah Biennale Foundation’s Public Programs Building, Ariel André and GOLEM designed modular collage tables with edges that leave gaps when grouped. The studio identifies those gaps as passages for cables. For a similar workshop, put the gap on the furniture maker’s drawing and show the point of supply on the electrical drawing for each arrangement. Include the path between them and check where it crosses the floor people use. Give both drawings the same detail reference so a bidder can see where their work ends. ArchDaily, Diriyah Biennale Foundation Public Programs Building, workshop furniture

On a proposed library table, show the cable path in each approved layout. Include a person using the outlet and draw the table foot beside the floor box. If the tabletop shifts along the room between bookings, establish which configurations can use that box. Ask the furniture bidder to show the connector, the length and exit position of the furniture lead, and the means of accessing it. The engineer checks the supply and connection against the proposal. A cable can reach a connector on an empty plan and still cross the route used by a person approaching the table. Seeing who approaches from which side can change which end of the furniture takes the lead.

If a control panel also sits in the table, give its connection a separate reference. AVIXA's documentation standard covers identifying the information an audiovisual installation needs and the responsibilities for providing and tracking it. The furniture maker may need to cut an opening before the audiovisual equipment arrives. At tender, state who supplies the panel's mounting template and who checks it against the actual control unit before fabrication. Include the finish around the cutout in the priced item. AVIXA, Documentation Requirements for Audiovisual Systems, 2022

Put the same detail in both prices

The RIBA Plan of Work puts the coordination of design team and specialist design at Technical Design and uses a Responsibility Matrix to define their boundaries. England's Department for Education also provides for a Detailed Responsibility Matrix in its published Exchange Information Requirements. A matrix can give the design and information responsibilities a home. The scope and price schedule should identify the people supplying and fitting the actual parts. Put two linked scope lines beside the table detail. In this example one line prices the building supply and floor box, and the other prices the furniture outlets and lead. Give final connection and testing to a named package and state when that package can do the work. RIBA Plan of Work 2020 Overview, Technical Design and specialist subcontractor boundaries England Department for Education, Exchange Information Requirements, 2026, section D6

The US General Services Administration's P100 submittal matrix places furniture plans among the information to be coordinated in interior design. Add the installation order to your own plan. On an existing raised floor, an outlet position can be plausible until the electrician checks the panel grid below it. Give bidders the same drawing of that grid, and decide who prices a replacement floor panel if the proposed box lands across a panel joint. US General Services Administration, P100 Submittal Matrix, 2024, Interior Design

The exercise can also show what the tender needs to cover where a fixed module meets a substrate that varies along the wall or floor. Show the intended position of the fixing relative to the finished floor and say who verifies the substrate. In the United States, the AIA A201-2017 model general conditions address contractor review of submittals and field measurements. They also distinguish review and approval from acceptance of an undisclosed deviation. On the project schedule, set a point for reporting a discrepancy before the finish is cut. If the furniture bracket changes after the survey, trace who checks the substrate, who revises the bracket drawing, and who prices the repair to a finish already installed. AIA A201-2017, public Torrington project copy, sections 3.12.4 and 3.12.6 to 3.12.8

Before the lead designer issues the drawing, have the cost consultant read the two scope lines aloud with the detail in front of both trades. Ask each person to point to the last part and the last operation in their price. Add the name of the person who will witness the connection test. If the scope depends on work covered by a third package, enter the reference and the needed installation date on the same sheet before the tender goes out.