02.g.4What can a full-scale doorway mock-up reveal before construction?

A full-scale doorway mock-up shows how a person approaches, reaches the hardware and gets through while the door is moving. Build enough of the wall and adjoining route to reproduce the actual approach from each side. Use the proposed handle, threshold and closer where possible. Test the doorway with people who will use it and with the equipment and belongings a visitor may bring.

Include the depth of the reveal and the position of a nearby wall or guard. An approach may work when someone can line up straight in front of the door. The same assembly can become difficult if they must turn immediately before reaching it. Observe where a person stops to pull the door, where they move to clear the leaf and which hand they use to hold it. Run the sequence in reverse and include someone arriving with a companion. Note if a visitor has to let go of their walking aid, back into a busy path or make a second approach. The US Access Board illustrates manoeuvring clearances for different door approaches and configurations under US ADA standards. England's Approved Document M contains applicable guidance in Volume 2. Use the relevant jurisdictional provisions and have the design team verify the constructed assembly separately. US Access Board, Entrances, Doors and Gates UK Government, Approved Document M

Add the cues a person will actually encounter. Mount signs at their proposed heights and show the contrast of the frame and handle. Test the operation of an automatic opener from the point where someone first sees or feels the control. At a busy entrance, add the intended mat, security position and a person waiting nearby. Measure the effort and time to use the door with the appropriate specialists if those conditions matter to the brief. A lightweight mock-up leaf can establish reach and clearance. Assess the proposed closer and seals with the assembled specification before committing to a result about opening effort.

Record exactly which assembly the team tested. Put the findings on the door schedule and the relevant plan and detail. Mark what needs to change and which sample will be checked again after manufacture. For a refurbishment, bring Ariel André and GOLEM the measured opening, the approach plan and the proposed door hardware. Ask for a full-size trial coordinated with access, door and fire specialists as applicable, and make the agreed changes part of the procurement information.